RASLAG [ASLAG] debuted strongly on its first trading day in the stock market on June 6, 2022. The listing ceremony was hosted by the Philippine Stock Exchange, Inc. (PSE) with the ticker “ASLAG” which traded ₱569 million on its listing day, making it the second most active stock by value-added.

The IPO raised ₱700 Million that will be used to fund the equity portion of RASLAG-4’s development and construction and the pre-development works for RASLAG-5, and other general corporate purposes.

ASLAG President, Chairman and CEO Peter G. Nepomuceno said: “Throughout our history, the Nepomuceno Group has been guided by my parents’ motto, “Do it well or not at all.” It is this simple but timeless principle that motivates us in Raslag Corp. as we aim to become a major renewable energy player in the country.”

Mr. Nepomuceno also expressed pride in the company’s fundamentals and its future and stated that ASLAG has a clear strategy to achieve a 10-fold growth of its current solar portfolio in the next ten years of 250MW. With the third venture ready for energization, it would nearly double RASLAG’s generation capacity.

According to Mr. Monzon, “The listing of Raslag will grow the portfolio of companies in the Renewable Energy space in our stock market.  As an advocate of sustainability, being a member of the Sustainable Stock Exchanges Initiative, the PSE understands the crucial need for renewables in the fight against climate change. I am pleased that through this IPO, the PSE was able to support Raslag’s capital-raising activity”.

As Mr. Monzon cited, the LSE tranche of ASLAG was oversubscribed by 1.5 times.  ASLAG IPO hit the market with the first of its trades coming through at ₱2.48/share which represented a 24% gain over the offer price of ₱2.00/share with ₱128 Million traded in the first five minutes. The day trade ended in a finish of ₱2.05/share

Sources:

https://corporate.pse.com.ph/raslag-corp-holds-maiden-share-listing/

https://www.philstar.com/business/stock-commentary/2022/06/07/2186656/raslag-ipo-started-wild-ended-mild

LATEST NEWS

October 17, 2023

RASLAG welcomes Ms. Imelda Tiongson as Independent Director

Aslag Corp. welcomes Ms. Ida Tiongson as its new Independent Director. Ms. Tiongson, who is also incoming Vice Chairman of the Institute of Corporate Directors, comes with a wealth of expertise in Governance, Risk Management, and Financial Technology. Her appointment at Raslag Corp. aligns with the company’s strategic goal to
July 11, 2023

RASLAG IV 36.646 MWp Construction Updates – July 2023

The fourth venture of RASLAG Corporation (RASLAG IV), which is located on a 25.2-hectare (251,750 sqm.) plot of land in Barangay San Pablo (Talimundoc), Magalang, Pampanga, is set to boost RASLAG’s current energy portfolio by 36.646 MWp, inching closer to the company’s 250 MWp pipeline and is expected to begin
June 30, 2023

RASLAG Corporation’s Annual Stockholders’ Meeting Video Presentation

By harnessing the power of the sun, we are not only reducing our carbon footprint, but we are also leaving a legacy of environmental stewardship. Lighting the future with renewables, we are RASLAG Corporation.
July 8, 2022

ASLAG eyes revenue growth for its third venture plant

ASLAG expects P215 million in revenues for its third venture plant Raslag 3 was energized on July 8, 2022, and prompted the start of its testing and commissioning. This milestone commenced immediately after the receipt of Provisional Approval to Connect to energize as a Generator from the National Grid Corporation

 

Stay up to date

Enter your email below to be notified about Openings.

    June 6, 2022

    ASLAG Goes Public

    RASLAG [ASLAG] debuted strongly on its first trading day in the stock market on June 6, 2022. The listing ceremony was hosted by the Philippine Stock Exchange, Inc. (PSE) with the ticker “ASLAG” which traded ₱569 million on its listing day, making it the second most active stock by value-added.
    April 6, 2022

    RASLAG III 18.011MWp Construction Updates – March 26, 2022

    RASLAG III 18.011MWp Solar PV Plant Project is closer to fruition with target commercial operations date on May 16, 2022 to double its portfolio to 41.198MWp.
    February 11, 2022

    Pampanga’s Peter Nepomuceno goes big on solar power

    Power industry veteran Peter G. Nepomuceno is making a big push into solar energy, with the goal of ramping up Raslag Corp.’s generation capacity by more than 10-fold in the next 10 years.
    January 11, 2022

    RASLAG III 18.011MWp Construction Updates

    RASLAG Corp’s third venture sits at 12.8-hectare property of Barangay Bical, Mabalacat and Brgy. San Jose, Magalang, Pampanga that once completed, will double its solar portfolio of the to 41.198 MWp and is expected to be operational...